20/7/22 - UPDATE - Works have been delayed due to fencing panels not being available through the contractor.  Works should commence in mid-August and not the beginning as first informed.

16/6/22 - UPDATE - Calor gas has confirmed works should take place from 1st to 5th August.

14/6/22 -  Today I received confirmation from Calor Gas Customer Engineering Co-ordinator that their site visit is complete.

This is the information they supplied to me.

Further to our engineer's visit yesterday he has advised the following

Not Complete - Customer Notes: Compound fence has all broken and fallen down, I have put the gate and piece of the fence back up but this needs a new fence and membrane with gravel urgently

We will need to replace this like for like with half hit and miss and another half chainlink we will need to order the following materials -

20m of chainlink fencing with 2 gates

12x hit and miss fence panels with 14 posts and 40 bags of postcrete

Fencing to be delivered on day 2

The following are to be delivered on day 1-

8-yard skip delivered

3 heras fence panels with feet

1-ton digger

Skip loading dumper

3 rolls of weed suppression

8-ton bags of p gravel delivered on day 4 the first drop

Hopefully, this work will be carried out soon.